Editing Split Orders

If you want to edit a split order, follow the instruction for other order types in Editing a Purchase Order (PO).

Note

After splitting into partial orders, you no longer have the option to automatically recalculate the total split. Changes to the amounts in the partial orders will then also change the total amount.

To edit partial orders from an overview:

  1. From the sidebar navigation, click > Planner > Calendar or > Budget and navigate to the element with the assigned split order.

  2. Double-click the element to open the detail view.

  3. Switch to the Orders tab.

  4. Click the icon next to the partial order.

    An overview appears showing all orders related to this split order.

  5. Click the icon next to the split order you want to edit.

    The editing dialog for the split order appears.

  6. Make your changes to the order.

  7. Click Save.

You have successfully edited the split order.